Navigation:Home >> Business >> International Project
Brunei PMB Island Bridge, subgrade, and utility en
Published:2018/2/2

The project is located on the east side of Brunei capital, across SerasaBay, connecting Brunei island and Pulau Muara Besar Island, with a total length of 5915m, of which the length of the sea crossing bridge is 2680m. According to the "two-way four lane + emergency lane" standard construction. The main bridge is a 80+120+120+80m variable cross-section prestressed concrete continuous rigid frame bridge, and the approach bridge is 60m span section precast beam. The box Liang Kuan 23.6m adopts single box and single chamber section.